Completed work
                        - Dismantling work and special labor were implemented before the production work. For instance, three metal tanks of sewage treatment plants and the old sewage treatment plant building were dismantled. A retaining wall was made between the newly erected structure and the reservoir. The wall's length is 18 m, and the length of the piles is 8 m.
 - General construction work - complete cycle, digging, and concrete work. Installation of metal structures with subsequent induction of sandwich panels.
 - A complex of installation work was implemented on internal water supply networks, sewerage, ventilation, heating systems, and wiring.
 - The installation of technological equipment with piping and a complex of electrical installation work has been implemented. The installation of technological equipment was completed in a short time at the existing production.
 - Improvement of the adjacent territory was completed by laying road slabs and landscaping the area.